A lorry washing bay has no single correct length, door height or floor fall. Those three dimensions come from the tallest and longest vehicle you will ever put through it, and from a site engineer and the local sewer authority who sign off the slab and the drains. This article does not quote a number for any of them, because the US sources we checked do not give one. What it does give is the order in which to make the decisions, and the drainage chain that has to work whatever the dimensions turn out to be.
In the US the same structure is usually called a truck wash bay. Lorry is the UK term, and you will see both in search results. The planning questions are the same on either side of the Atlantic, but the rules are not, so this article keeps to US guidance and does not borrow length or height figures from UK or EU sources.
Start with the vehicle, not the building
The common mistake in building a truck wash bay is to design the shell first and ask what fits inside later. Work the other way round. Write down the vehicles the bay must serve today, and the ones you might add in the next few years. Then let that list set the envelope.
For each vehicle type, record:
- the overall length, including any trailer, drawbar or rear-mounted equipment;
- the overall width at the widest point, including mirrors and any side fittings;
- the overall height at the highest point, including roof-mounted fans, beacons, aerials, air deflectors and anything that is raised when the vehicle is parked;
- whether the vehicle is a rigid truck, a tractor with trailer, a tanker, a tipper, a refrigerated unit or something specialised;
- whether the trailer is washed attached or detached.
Take the tallest figure and the longest figure from that list, not an average. A bay that suits most of the fleet but not the one tall refrigerated unit or the longest combination will turn into a bay you work around, and that costs more time than a slightly larger slab would have cost to build.
Measure real vehicles on a real day where you can. Brochure heights and lengths leave out the fittings that were added after delivery.
How bay length is really decided
Length is more than the vehicle plus a little. The engineer and the machine installer will need to agree an allowance for each of the following, and none of them has a standard figure we can responsibly quote.
- The longest vehicle or combination. This is the base figure, from your list above.
- The wash equipment itself. A gantry or other machine needs room to park at one end and room to travel the full length of the vehicle. The installer will know the machine’s footprint and travel.
- Working space. If staff pre-treat, detail or inspect, they need room to walk around the vehicle safely, with a drained, dry place to stand where that is feasible.
- Approach and exit. The driver should be able to position the vehicle without several attempts. A bay that needs shunting to line up will be slow and will damage doors and kerbs over time.
- Splash and overspray. Spray travels. The contained slab, not just the vehicle footprint, has to catch it. This is the allowance that most often gets underestimated.
It is worth asking the installer how the machine’s wash path relates to the slab edge, and asking the engineer how the containment edge relates to the wash path. Those two conversations should produce one agreed drawing, not two separate ones.
Single bay or through lane
A drive-through layout lets vehicles enter at one end and leave at the other, which avoids reversing. A single-entry layout can take less land but needs a clear turning area. Which is right depends on your site, your traffic and where the queue will stand. Draw the queue as well as the bay. A bay that backs vehicles onto a public road or across a fuel island will not work however good the equipment is.
Door height: clear opening, not nominal opening
Door height is set by the tallest vehicle, but the figure that matters is the clear opening once the door, its track or motor, any lighting and any pipework are in place. Ask for the clear height in writing and compare it to your tallest vehicle with its roof fittings.
Things that reduce the clear opening in practice:
- the door mechanism and its housing when the door is open;
- lights, sensors, signs and cable runs fixed near the opening;
- overhead water, air or chemical lines;
- the bay’s own equipment, if a gantry or boom travels near the entrance;
- a rise in the slab at the threshold, if the falls bring the floor up towards the door.
Allow for a vehicle that is taller than normal because of its load or because its suspension is pumped up. Agree the clearance and splash allowances with the engineer and the installer before the door is ordered, because changing a door opening after the walls are up is expensive.
Ventilation and condensation also affect the door decision. A closed bay full of warm, wet air needs somewhere for that air to go, and doors, vents and any extraction should be considered together. That is a question for the building engineer, not a dimension we can give.
Falls: what the guidance says and what it does not
Falls are the slopes in the slab that move wash water to the drain. We could not find a US federal or industry source that sets a slope ratio for a truck wash bay, so any percentage or ratio you see quoted should be treated as a local or engineer-specific figure, not a rule.
What the US Environmental Protection Agency (EPA) does say is useful in principle. Its stormwater best-management-practice sheet for municipal vehicle and equipment washing describes wash areas as designated areas with drainage that lets wash water be contained and collected, using features such as gratings, raised platforms and bermed areas. When installing a wash area, it advises paving to minimise loss of wash water, and using a berm or sloping to contain the wash water and direct it to a sump.
That sheet is municipal guidance rather than a commercial truck wash rule, so read it as good practice. It still tells you the shape of the design: a paved slab, a way to keep water on it, and a fall or berm that leads to a single collection point.
What a good fall has to achieve
Rather than a slope figure, think about outcomes and ask your engineer to show how the design delivers each one:
- No ponding. Water should not sit in low spots, where it carries dirt back onto tyres and becomes a slip hazard.
- Direction. Water should run towards the drain and away from doors, walkways, equipment cabinets and the place where staff stand.
- Containment. The edges of the slab, whether bermed, kerbed or sloped back, should hold the water that the wash path throws outwards.
- Traction. A finish that drains well but is slick under a wet tyre or boot is not a good result. Surface finish is part of the falls conversation.
- Practical cleaning. Silt and road grime settle in the sump and drain run. They should be reachable for cleaning without taking the bay apart.
- Vehicle geometry. Long vehicles with low rear overhangs and trailers on a gradient can behave differently from a car. The engineer should check the fall against the vehicles you actually run, including how it affects door clearance.
A steeper fall is not automatically better. It can affect how vehicles sit, how the door clears and how staff walk. The right figure is the one your engineer can justify for your slab, your drain and your vehicles.
The drainage chain, from slab to discharge
Whatever the bay dimensions, the drainage chain has the same stages. The EPA guidance sets them out in plain terms, and it is worth building your plan around them.
- A paved, contained slab with a berm or fall that keeps wash water on it and directs it to a sump.
- A sump or collection point where the water gathers and the heavier solids settle.
- Treatment, generally an oil/water separator or something similar.
- A destination: a sanitary sewer connection the sewer authority has approved, a holding tank, a process treatment system or an enclosed recycling system.
The EPA sheet says the sump can connect to the sanitary sewer, a holding tank, a process treatment system or an enclosed recycling system. It says treatment systems generally include oil/water separators or something similar, and that regulations often require them where the wash water goes to the sanitary sewer. It also advises covering the wash area when it is not in use so that rain stays out. That matters most for open or part-open bays, where rainwater would otherwise add to the load on the drain and the separator.
One rule underlies all of this: wash water must not reach a storm drain. If your site has a storm drain near the bay, say so early, and make the engineer show how the containment keeps water away from it.
Oil/water separators need looking after
Trucks bring in more than dirt. Fuel, engine oil and hydraulic fluid come off the underside and wheel arches. EPA’s archived sector notebook for truck transportation says oil/water separators are typically connected to floor drains or wash racks, and that they need periodic servicing. The notebook is archived and undated, so use it for that general point only. For your site, the practical consequence is to allow access to the separator for servicing, and to include that servicing in your running plan from day one.
Phone the sewer authority before you finalise the design
The most useful call you can make in the planning stage is to the local sewer authority. The discharge limits for a truck wash are local, so the drain you design has to match what that authority will accept.
According to the International Carwash Association research paper on water effluent and solid waste, more than 99 percent of professional car washes discharge their effluent to a sanitary sewer and a publicly owned treatment works (POTW). The paper says the POTW sets pretreatment guidance or discharge limits, usually through a local ordinance or a sanitary sewer district’s rules. It also says no federal discharge limits have been issued specific to commercial car washes, that limits may come from states or local ordinances, and that local rules may be stricter but not more lenient than federal standards. The paper is undated and concerns car washes rather than heavy trucks, so treat it as an explanation of how the system is structured, not as a statement of current rules for your site.
The same paper says a National Pollutant Discharge Elimination System (NPDES) permit is for facilities that discharge directly to surface waters, and that facilities connected to a municipal system, on septic, or with no surface discharge do not need one. Whether that applies to you depends on your discharge route, so confirm it locally.
The EPA truck transportation notebook gives the same practical advice from the trucking side. It says facilities should contact their POTW to learn whether pretreatment requirements or limits apply. It notes that contacting the POTW is not itself a federal requirement, but that the facility could be liable if it discharges improperly. The EPA municipal sheet makes a matching point: if you want to connect to the sanitary sewer, seek the sewer authority’s permission first, because wash water may have special treatment requirements.
Questions to ask the sewer authority
- Is a connection for truck wash water acceptable at this address, and under which rules?
- Is an oil/water separator or other pretreatment required, and to what standard?
- Are there limits on what the discharge may contain, and how are they monitored?
- Do you need a permit or written approval before connection, and who issues it?
- If sewer connection is not possible, is a holding tank with collection, or an enclosed recycling system, acceptable?
Write down the answers, and ask who at the authority gave them. Those notes will matter when the engineer draws the drain and when you apply for permits.
A note on floor drains and the ground
If your bay sits inside a building that also houses vehicle repair or maintenance, you may come across the EPA rules on motor vehicle waste disposal wells. EPA guidance says the Underground Injection Control Class V rule banned new motor vehicle waste disposal wells as of April 5, 2000. It prohibits new floor drains and sinks that receive fluids from vehicle repair or maintenance and discharge to the ground. EPA’s compliance guidance on vehicle waste disposal says such floor drains must go to a holding tank or sanitary sewer, must never connect to a storm drain, and that a sewer hookup must be approved by the local sewage treatment plant.
Those rules are written for vehicle repair and maintenance areas, not specifically for wash bays. They are included here because they point the same way as the wash-area guidance: a floor drain in a vehicle area should lead to a controlled destination, not to the ground and not to a storm drain. Ask your engineer and the local authorities whether they apply to your layout.
Wet floors and the people who work on them
A wash bay is a wet process by definition, and the people who work in it need a surface that is drained and as dry as practical. The Occupational Safety and Health Administration (OSHA) standard on walking-working surfaces, 29 CFR 1910.22, requires floors to be kept clean and, as far as feasible, dry. Where wet processes are used, drainage must be maintained. Where feasible, dry standing places such as false floors, platforms and mats must be provided. The standard also requires walking-working surfaces to be free of hazards such as leaks and spills, and to be inspected and maintained.
The standard does not set a slope, a drain spacing or a surface finish, so it cannot tell you how to build the slab. What it does is fix the design objective. The falls and drains should keep water away from the places where staff stand and walk, and the maintenance plan should include inspecting the surface and clearing the drains. If your wash process involves staff working beside the vehicle, include a drained standing area in the layout from the start rather than adding mats afterwards.
How the wash method affects the bay
The method you choose changes what the bay must contain. EPA’s WaterSense guidance on vehicle washes groups vehicle washes into three types: conveyor, in-bay automatic and roll-over style. It notes that in-bay automatic and conveyor facilities can benefit from water reclamation systems. That guidance is aimed mainly at car washes, and we did not find a water-use figure for heavy trucks in it, so do not use car wash water figures to size a truck bay.
For layout, the main point is practical. A machine that moves along a stationary vehicle needs a different slab and door arrangement from a bay where staff wash by hand. A system that reclaims water changes the sump and tank requirements, and may reduce how much goes to the sewer, though that depends on the system and on what your sewer authority permits. Decide the wash method early, because the engineer needs it to design the containment and the drain.
A sensible order of work
- List the vehicles and record the tallest, longest and widest, with fittings.
- Choose the wash method and speak to the installer about the machine’s footprint, travel and services.
- Call the sewer authority and record what it will accept and what pretreatment it expects.
- Brief the site engineer with the vehicle list, the wash method and the sewer authority’s answers. Ask for length, clear door height, falls, containment and drain layout as one drawing.
- Check the drawing against your queue and your approach and exit routes.
- Plan the separator, sump and drain servicing and decide who does it and how often.
- Confirm permits and approvals before work starts, not after.
Doing the sewer call before the engineer’s drawing saves rework. A drain designed for the wrong destination is a slab you may have to cut up.
What to take away
The dimensions of a lorry washing bay are answers, not starting points. The vehicle sets the length and the clear door height. The engineer, working from your vehicle list, your wash method and the sewer authority’s rules, sets the falls and the drain layout. The EPA guidance gives the structure: a paved, contained slab sloped or bermed to a sump, then treatment, then an approved destination, with nothing going to a storm drain. OSHA’s standard gives the safety test: staff areas drained and kept as dry as feasible.
Where Europe Makine fits
Europe Makine manufactures wash systems and builds turnkey car washes, including the SUNRISE W4000/W4700 heavy vehicle wash, which on client figures from November 2026 washes about 6 vehicles an hour. We have not published bay dimensions, door heights or clearances for it here, because they depend on the site and the vehicles, and are best agreed with the installer and your engineer. For a turnkey project, the work includes securing the site, clearing permits, installing and calibrating the machines, and handing over a running operation, which is where the sewer approval and drainage questions above get resolved in practice.